Nuclear Power Station Biblis
Jan. 2, 2004
The two blocks A and B of the nuclear power station Biblis with an achievement of together approximately 2,500 MW went 1974 and/or 1976 to the net and set at that time both national and internationally technical yardsticks. The availability factor is on the average with 74 %, those to time availability with approximately 76 %. over 400 billion a KW/H until today was produced. The production corresponds to requirements of electric current of 6.5 million households in Germany.
Data, numbers, facts
| Block | A and B |
| Type | Pressurized water reactor |
| Area of application | Basic load |
| Start-up | Block A: 1974, block B: 1976 |
| Fuel | Uranium 235 |
| Kraftwerksleistung (netto) | 2407 MW |
| Reactor pressure | 155 bar |
| Steam temperature | 265.2/272.5 Degrees C |
| Fuel weight | 102.7 t |
| Cooling | Fresh water/forced-draught cooling tower |
| Number of Brennelemte per block | 193 |